34.2 Approval Process

Capital improvements are developed in accordance with policies and procedures set by the Board of Regents, State of Iowa, and are accomplished by University administration in consultation with existing committees and facility users. The approval process for capital improvement projects is dependent on the project's budgeted costs

New Building Construction

< $250,000 Approval is delegated to University administration
>= $250,000 and
< $1 million
Approval by the executive director of the board office
>= $1 million Approval by Board of Regents

Existing Building Renovation

< $250,000 Approval is delegated to University administration
>= $250,000 and
< $2 million
Approval by the executive director of the board office
>= $2 million Approval by Board of Regents